1. Discharging the fixed toothed disc, as long as unscrew the bolt.
2. Discharging the bearing. First, open the main cavity. Second, unscrew rotation toothed disc or rotation cutter. Third, taken to the closed interior design and center bearing cap. Forth, discharge the side pulley and bearing caps, then respectively pull out the axial and bearing both ends.
3. At the time of installation, the shaft sleeve oil hole is still kept at the oil eye.
4. Installing the screen, the screen ring should be close to the shoulder groove tightly. Or damage the screen when closing the door.
5. Making the screen ring, mesh expansion length should be according to screen making shoulder diameter circle, if damage should be done to screen manufacturers.
6. Installation screen: two screen alignment when combined within the mark screen is then pressed into the screen, if the mesh is too tight, screens can be curved into the porch, then push outward.
7. WF series universal mill, has a feed hopper upper, a feed control board below the feed hopper. Please adjust the board to the suitable position upon the material brittle and grinding fineness, then lock it tightly.
8. The discharge door is below the machine. If there is a little spray when the material is discharged with the wind, then should add a bag on the discharge door tightly. Let the material overflow through the bag slowly.
9. Before the first start, should be carried out a commissioning. Before commissioning, check all parts of the machine to confirm whether the machine is qualified.
10. The machine has water cooled type. Should add some oil to avoid the damage of the bearing when use.